Watch a 1 million pound converter being moved in a 3-month timelapse, compressed into 60 seconds.

Bartow

1 Million Pound Steel Sulfuric Converter Relocation

Gulf Coast industrial successfully relocated a prefabricated stainless steel sulfuric converter weighing one million pounds to its new location, 80 feet away. We then connected all the pieces and ducting of the converter system. The sulfuric converter tower contains the catalyst that stimulates the chemical conversion of gases for the production of fertilizers.

Job Stats

  • 47 days, 20,000 hour incident and injury-free work hours

  • Gulf Coast Industrial moved a 1 million pound prefabricated stainless steel converter 80 feet to its new location

  • Connect all the pieces and tied them in the ducting for the converter system

     

 

Apollo Beach

Explore a massive 600,000-pound ship loader in just three months, captured in a breathtaking time-lapse condensed to just 60 seconds.

Apollo Beach

Emergency 600,000 Pound Ship Repair and Relocation

An emergency call was placed due to a mechanical issue with the ship loader. The Gulf Coast Industrial team was assigned to fix the loader, the boom cables, and the rail tracks and relocate the unit. However, while working on it, the boom cable snapped, causing the boom’s weight to slide backward, hitting the main unit, tearing the rails out of the ground, and derailing the loader.

Job Stats

  • 9000 work hours completed incident- and injury-free

  • Put derailed 600,000 pounds ship loader back on the track

  • Repair metal support structure, loader support systems and replace boom cabling

  • Lifted equipment to make repairs and replace structural steel.

  • Jack the ship loader, install then remove temporary rails, and install new rails from the damaged point

  • Push the loader down the temp rail to the existing rail

 

Mooreharen

Follow the Gulf Coast Industrial team as they complete a 3-month hopper installation project in this exciting 60-second timelapse.

Mooreharen

One Million Pound Hopper Installation

Check out this incredible timelapse video of a three-month project completed by the Gulf Coast Industrial construction team. The video shows the entire project in just over 60 seconds! Despite facing challenges such as a shutdown due to a hurricane in central Florida, the team managed to install one million tons of equipment within 90 days, working around the clock.

Job Stats

  • 9000 work hours completed incident- and injury-free

  • Put derailed 600,000 pounds ship loader back on the track

  • Repair metal support structure, loader support systems and replace boom cabling

  • Lifted equipment to make repairs and replace structural steel.

  • Jack the ship loader, install then remove temporary rails, and install new rails from the damaged point

  • Push the loader down the temp rail to the existing rail